May 27th 2025

UPDATE: PBPN Health Center C-Wing Addition

Lots of progress at the PBPN Health Center C-Wing Addition project. Job superintendent Randy Frahm and crews have much of the interior work underway including insulation of exterior walls and sheetrock being installed.  Mechanical, electrical and plumbing rough ins are completed and work in the overhead is underway. For the exterior, the roof framing is complete, underlayment and roofing installed, and the prefinished metal coping puts the finishing touch on the roof systems. The façade is a mix of exterior insulation finishing system (EIFS) and masonry veneer.