UPDATE: PBPN Food Sovereignty
April 3rd 2026

UPDATE: PBPN Food Sovereignty

The PBPN Food Sovereignty project is moving right along.  Job superintendent Randy Frahm and crews have the standing seam metal roof panels installed and the seaming process is underway.  The metal wall framing and exterior wall system along the east and north side of the structure are nearing completion.  Soon mechanical, electrical and plumbing rough-ins will begin.