UPDATE: PBPN Food Sovereignty Project
February 20th 2026

UPDATE: PBPN Food Sovereignty Project

The PBPN Food Sovereignty Project is moving right along.  Job superintendent Randy Frahm and crews have started with the erection of the superstructure. The mainframe of this building is comprised of a Manufactured Metal Building. An expansive mechanical pad will be required to make space for all the mechanical equipment needed. The site grading for this is underway and soon the concrete will be placed and finished.