Projects Update – Plastikon Healthcare

Plastikon Healthcare, in the East Hills Business Park, is one of the projects Mar Lan has been finishing. The shell warehouse building was turned over to Plastikon in late November and the focus was put forth to complete the clean-room manufacturing suites. The arrival of the IMM machines and Robots in Mid-December was met with great excitement to see these massive machines weighing over 70,000 pounds installed.  Project completion is scheduled for January.  All involved in the project have really stepped forward to get this fast-track schedule completed and everyone is eager to see these machines in operation. A formal ribbon cutting ceremony will be held in Spring 2019.