Home Sweet Home Dog Resort is coming along nicely. The building dry-in is completed and the metal roofing is underway. The exposed cedar truss entry system has been installed and will add a really nice accent to the entry doors. Site utilities are underway and nearing completion which will allow us to start on the concrete and asphalt that make up the parking lot and sidewalks. Inside the building, interior walls are in place and mechanical and electrical rough-in have started. Jason Kellogg, the project superintendent has had his fill of wet weather. While weather will continue to affect the site improvements, the building interior tasks are able to proceed, that is a bonus! The project is looking great and we’re super happy with the progress at this project!